|
Floorheat Australia
Contract Conditions
2003
1.0 GENERAL
1.1 Acceptance period
The price quoted in this quotation is valid for 30 days of the date hereof
or any further extension as Floorheat Australia
(hereafter referred to as FHA) may allow in writing. If no prior
extension has been granted, FHA reserves the right to revise this
quotation.
1.2 Scale of Work
The Customer acknowledges that the quotation does not include any
Electrical work, or any other work not specifically referred to in the
Quotation Schedule or the attached specifications referred to in the
quotation.
2.0 PRICE AND TERMS OF PAYMENT
2.1 The Price
The prices referred to under Quoted Price overleaf is for the extent of
work set out in the Quotation Schedule only, and includes items that would
reasonably be expected to complete the work detailed overleaf. It does not
include any electrical work, unless specified.
2.2 Loading Adjustments
At the time of installation the Electrical Loadings installed may be
increased or decreased from the amounts quoted due to minor changes to
areas or zones to be heated. No price change will occur if these changes
increase or decrease the loadings quoted by +/- 20%.
2.3 Variations to Work
The scope of work including any materials may only be varied by written
agreement between FHA and the Customer or their representative. The
agreement must set out the additional or omitted work and materials, and
any change to the completion date. The variation agreement must be signed
and dated by both parties. The price for any variations will be adjusted
to show an increase or decrease in the Quoted Price. In addition to the
price referred to in the Quoted Price, FHA is entitled to charge
extra for:-
-
Attendance to the site for any stage of
work at the Customer or representative's request, when the job was not
ready to proceed.
-
Work requested to be done outside
normal working hours (Monday to Friday - 7.30 am - 4.00 pm).
-
Increases in the cost of labour and
materials, if for reasons beyond the control of FHA, work cannot be
completed within 6 months of acceptance.
-
Re-design or changes to the heating
installation as a consequence of building plan or government
legislation amendments.
-
For in-slab cable installations, extra
site attendances for the testing/monitoring of cables, where
concreting involves a greater number of concrete pours than that
detailed in the number of site visits allowed for overleaf.
-
Repair or replacement of materials
damaged or stolen on site by any person or cause beyond the control of
FHA.
-
If Section 4.0 is not adhered to.
2.4 Terms of Payment
The Customer must pay the contractor the Quoted Price in full, or as
invoiced in stages by FHA in the manner shown in the Payment Terms
overleaf. The prompt payment discount can only be deducted if FHA receives
the full invoiced amount less the discount shown within 2 days of the
installation or invoice date.
2.5 Default, Cancellation and Delays in Payment
Should an Invoice become overdue, it is subject to interest at the rate of
1.5% per month or part thereof, plus any expenses incurred in the recovery
of the overdue account. In the event of cancellation the Customer shall
pay to FHA the following:-
-
The value of work commenced by FHA for which no remuneration has been
received, including preparation of drawings, specifications, manufacturer of equipment and special materials purchased by FHA on behalf of the
Customer.
-
The sum equal to ten per cent (10%) of the price payable as and for
liquidated damages.
2.6 Retention of Title
FHA may at its discretion remove all equipment, goods and materials that
form part of any overdue account, the Customer shall not hinder such
removal. Until payment in full for the work done or a section thereof is
received by FHA, the Customer shall hold the works or the unpaid section
thereof and any other works manufactured therefrom or incorporated therein
as bailee for FHA, provided however that the Customer may sell any of the
works in the ordinary course of its business on condition that should FHA
so require the Customer will assign to FHA its rights in respect of the
sale price thereof.
3.0 HEATING DESIGN AND PERFORMANCE
Heating Design Basis
The heating design and layout is based on information, plans or
specifications supplied by the Customer (FHA will not be held responsible
if heating cables are not installed in the correct locations due to the
failure to supply current drawings & measurements), together with the
assumption that thermal insulation to the equivalent of R2.5 is to be
installed into the ceilings, except when Ceiling Heating is to be
installed, in which case this level is to be increased to R3 or as
specified.
Design temperatures are normally 160C in bedrooms, bathrooms, laundries,
WC's plus any other areas designated as background heated and 190C for
living areas.
In areas where the outside temperature frequently drops below 00C, any
in-slab installation shall include installation by the Customer of a
minimum of 25mm thick polystyrene or similar high quality insulating
product around the perimeter of the slab, to a minimum depth of 600mm.
Where suspended slabs are heated and the underside is exposed, the
underside shall be insulated by the Customer, with a minimum of 50mm thick
polystyrene or similar high quality insulating product.
Where Off-Peak is used, double glazing is recommended or windows must be
covered at night with heavy drapes with pelmets (open weave fabrics are
unsuitable).
The electricity supply to the heating system must be capable of
maintaining 240V +5% to the proposed heating circuits.
For quotations for heating under timber floors - devireg Floor/Air Thermostats 'floor temperature limiters'
must be set no higher than 28ºC.
4.0 CUSTOMER RESPONSIBILITY
It shall be the responsibility of the Customer to ensure that the
following requirements, recommendations and conditions are observed and to
accept full responsibility for the consequences of any lack of attention
to these matters. FHA will not be responsible for the consequences of any
disregard of these customer responsibilities:-
-
To ensure that an adequate electricity supply is available.
(Electrical loading in kW's per zone is provided on the Quotation
Schedule)
-
Arrange a time with FHA to attend the site to carry out installation
of the heating cables/foils, providing at least 14 days notice.
-
To acknowledge the thermal insulation requirements stated under
"Heating Design Basis".
-
To comply with the following specifications and to pass onto all
trades the relevant specifications.
4.1
-
In-Slab Heating - See Specification (SLS2002)
-
In Screed/Under Tile Heating in mortar beds - See
Specification (SCS2002)
-
None of the above floor heating systems shall be operated for a
period of 30 days from installation to allow the concrete/screed to cure
at its normal rate. The heating shall not be operated with materials or structures placed on
any heated area in such a way as to restrict adequate heat dissipation
from the floor, this includes items such as bean bags, mattresses or
furniture over 600mm wide resting flat on the floor with no openings
beneath. Such items may generally be positioned close to the perimeter
without this restriction.
The customer must check the cable layout to ensure that no
misunderstandings have occurred with respect to proposed wall and cupboard
installations.
If construction joints are to be included in the floor construction, or
changes made in the building plan, these must be clearly indicated on a
revised plan, which must be received by FHA prior to installation.
4.2 Ceiling Heating - See Specification (CHS2002)
Unless otherwise stated, the quotation is based upon standard 400mm or
600mm centres for ceiling battens, any variations to this may result in
the need for non-standard elements, this could result in possible delays
and pricing adjustments.
4.3 Under-Timber Floor Heating - See
Specification (UTS2002)
4.4 Thermostats - See Specification (TS2002)
5.0 FHA RESPONSIBILITY; WARRANTY & INSURANCE
5.1 FHA will ensure that all its employees are covered under the Workers
Compensation Act and that Public Liability Insurance cover is maintained
to a value of not
less than $10,000,000.00.
5.2 Warranty
All installations carried out, and any controls or equipment manufactured
by FHA are warranted against defects for a period of 7 years. FHA warrants
that all materials shall be of high quality, and be installed in a
workmanlike manner and in accordance with the specifications and
instructions issued by the manufacturers of materials used. FHA further
warrants that if defects are discovered in materials or equipment
manufactured by others, then FHA will assign, transfer and subrogate to
the Customer, all rights or benefits of respective manufacturer's
warranties.
The liability of FHA is limited to the above warranty and does not
included any other costs, claims or damages in relation to any of the
defects or matters consequented upon such repairs, excepting that the
Trade Practices Act and Fair Trading laws applying in Australia provide
the customer with certain remedies in the event that a manufactured
appliance fails due to defective materials or workmanship. This Warranty
is given as an additional remedy by FHA and is not meant to exclude, limit
or modify the manufacturers obligations under Federal or State Law.
FHA will not be liable for any damage caused by the customer or third
parties.
|