|
Floorheat Australia
devifoil™ Ceiling Specification
(CHS2002)
IMPORTANT:
The Electrical Schedule details Electrical Loadings, Thermostat Types and
any other accessories such as Contactors or Time Switches included in the
quotation.
Please refer to Thermostat Specification.
The Electrical Schedule/s together with
this sheet must be passed on to your Electrical Contractor and all
other relevant Trades, before you accept any quotation. This will
enable them to furnish you with quotations for any additional work which
will be required. Failure to do so may result in extra costs being
incurred by you.
General
Any
devifoil™ quotation is based
on the following information. The zones and electrical loadings of
the areas to be heated are set out in the Quotation
Schedule/Electrical Schedule:-
Our designs have allowed for
Ceiling timbers or battens being spaced at 400mm or 600mm centres
and up to 16mm of Plasterboard as Ceiling material. Ceiling lining
materials like lath and plaster or timber are not recommended. We
require 60-80% of clear ceiling space, wall to wall, with no
obstructions - this is to ensure that the full heating load can be
installed in each zone. If installation area available is
insufficient the total heat load cannot be installed and the
system will not work effectively. Before any installation can be
arranged, we must receive a ceiling plan showing the following:-
- All ceiling fixtures ie., light
fittings, air conditioning ducts, fans, speakers etc.
- Spacing, length and direction of
all ceiling timbers or battens that the ceiling material will
be fixed to.
All Gyprock/Plaster will 'move'
when heated - we cannot guarantee that the ceilings will not
crack. However, cracking may be reduced if the joints are able to
move.
NB:
Plasterboard must be fitted to Australian Standard AS/NZS
2589.1 (1997) and AS/NZS 2589.2 (1997) - 'incorporating the back blocking technique and paper
taped joints'. Control joints must be used where required. The use
of D122 or
D522
Probe/Air Thermostat is essential - this enables
the ceiling temperature to be pre-set to a maximum of 45oC - as
per manufacturers recommendations.

For ceilings where heating is to be
fitted from below:
The building must be airtight, and the insulation batts must be in
place. The Plasterboard/Ceiling must be installed without delay to avoid
damage to the elements.
When ceilings are already in place:
The Plasterboard/Ceiling Material must be in place. The surfaces
where the devifoils are to be installed must be clean and level,
and free from any sharp objects. The Insulation batts must not be
installed until after all the devifoils are in place. The
Insulation batts should then be installed without delay, to avoid any
damage to the heating.
|

|
 |
|
devifoil™ ceiling
foils with insulation batts (pink) installed above them |
Damage & Repairs:
Any damage caused to the devifoils by other trades, or by
wind or rain etc., will only be repaired upon receipt of a written work
order. Repair work will then be done on a 'do and charge' basis.
Insulation:
A minimum of 75mm Batt Type Insulation MUST be laid in
direct contact with the devifoils, ensuring that there are no air
gaps. The recommended minimum is R2.5 in Sydney. To obtain optimum
performance and efficiency the use of R3 is highly recommended. The supply
and installation of ceiling insulation is not included in our quotation.
If ceiling insulation is already installed,
we have not allowed for the removal or re-installation of any
existing insulation. Only Batt type insulation can be re-used where devifoils
are being installed. "Loose Fill" type insulation material can
only be re-used in areas where no devifoils are being installed.
Electrical:
The zones and electrical loadings of the areas to be heated will
be set out in the quotation. The Ceiling Heating must be
protected by a 30 mA Residual Current Device. It is the responsibility
of the site Electrical Contractor to:-
- Wire from Sub-Board/Switchboard to Room
Thermostat locations, then wire to ceiling space leaving 1 metre of
Neutral + Switch Wire in one corner of each room to be heated.
- Provide 1 empty 16mm or 20mm conduit
(with no more than a 90° bend) from Thermostat into ceiling space for
sensor probe.
- All loads over 2kW will require
Neutral + Switch Wire to be run from Contactor to one corner of the
room to be heated leaving 1 metre for connection to devifoil). Also
provide 1 empty 16mm or 20mm conduit (with no more than a 90º bend)
from Thermostat into ceiling space for sensor probe.
- Install any Thermostats, Contactors or
Time Switches provided.
- Wire from the Thermostat locations to
Sub-Board/Switchboard.
- Connect the heating to a 24 Hour Tariff
eg., Domestic or Time of Use.
It is the Electrical Contractor's
responsibility to organise any inspection required by the Supply
Authority.
|