Home
 
In Slab Installation Specifications
 
In Screed Installation Specifications
 
Ceiling Heating Installation Specifications
 
Under Battened Timber Floor Installation Specifications
  
Thermostat Specifications
 
Conditions Of Sale

Floorheat Australia

Heating Under Battened Timber Floors 
for Connection to Time of Use or Domestic Tariff

(UTS2002) 

IMPORTANT:
The Electrical Schedule details Electrical Loadings, Thermostat Types and any other accessories such as Contactors or Time Switches included in the quotation. 
Please refer to Thermostat Specification.

The Electrical Schedule/s together with this sheet must be passed on to your Electrical Contractor and all other relevant Trades, before you accept any quotation. This will enable them to furnish you with quotations for any additional work which will be required. Failure to do so may result in extra costs being incurred by you.

General

Any quotation for Under Battened Timber Floor Installations includes the design, supply and installation/fixing of all deviflex™ Heating Cables and the supply only of all Thermostats, Contactors or Time Switches quoted. The areas where the elements are to be installed must be clean and free from any sharp objects or debris. The insulation must be installed in accordance with the insulation information below.

Cabling that passes through joists or that is installed near the underside of floorboards must conform with Australian Standards Clause AS3.20.3.4. Our designs have allowed for up to 20mm of timber/flooring material, with floor timbers or battens being spaced at 450mm or 600mm centres. (See details set out below)

Under Battened Timber Floor Installation Cross Section

Even though the heating system will be controlled by a devireg™ combined floor and air sensing thermostat which incorporates a floor temperature limiter, it is recommended that you consult with the manufacturer or supplier regarding product suitability, maximum temperatures, moisture content and fixing methods. Experience has shown that most types of timber or laminated floor coverings can be used.

Under timber floor heating installation

cable loops run parallel to the timber battens

Under Timber Floor Heating can be installed on top of the concrete floor between timber battens

close up of cables installed beneath the timber floor

cables shown installed beneath the timber floor

close up of foil insulation required for this type of installation

photograph showing the insulation batts installed beneath the insulation foils

Under Timber Floor Heating can be also installed from underneath an exposed timber floor - 
please note the number of levels of insulation required for this type of installation (foils under the cables, as well as around the cables where they cross the joists, and insulation batts beneath the foils themselves)

To be Done by Others

Before cables can be installed, a floor plan must be supplied confirming the location of any cupboards, wardrobes or built-in furniture, and any floor level heating or cooling ducts etc. We will also require information regarding the thickness, spacing and direction of all timbers or battens that the timber/flooring material will be fixed to.

To allow for the proper installation of the heating cables, the builder/owner should ensure that prior to installation the relevant procedure listed below is carried out:-
For battened timber floors over concrete
: a gap of at least 50mm should be left at each end of the battens, this is to allow for the cable to pass between the battens.
For installations between timber joists: A 30mm x hole should be made (50mm below the underside of the timber floor), one at each end of the joists, to allow for the cable to pass between the joists.

Insulation

Supply and installation of insulation is not included in our quotation. A Minimum of 'R1.5' Foil Backed Insulation Batts is recommended below the heating system. The batts must be laid, foil side up and in full contact with the deviflex cables - there should be no air gaps below or to the sides. If this is impractical due to height restrictions with battened floors, the use of a Foil Backed Blanket similar or superior to 'Sarking' should be laid directly onto the floor surface (foil side upwards), as above.

Electrical

All Thermostats, Contactors or Time Switches quoted are supplied only, it is the responsibility of the Site Electrician to install and connect them. Contactors are supplied for any zone where individual loads are greater then the current carrying capacity of the Thermostat, (see Thermostat Specifications). Full electrical details are set out in the Electrical Schedule supplied.

Important - Please Note! - Two empty conduits must be installed by others as follows:-

  • For 'Cold Tails' one 20mm (minimum) empty conduit from the top of the void under the Timber floor to switch or thermostat position with a draw wire, must be provided for the 'cold tails'.
  • If more than One heating element is specified per zone, a separate empty 20mm conduit must be provide for each additional element. Please refer to the Electrical Schedule. See notes above )

close up of conduit installation for under timber floors

Notice that for each set of Cold Tails (each heating element) an extra conduit has been installed. Also note that the sensor probe conduit is installed between a cable loop.

  • For Sensor Probes a separate empty 10mm-16mm conduit must be installed for the remote sensor probes. This conduit will pass from the thermostat position down the wall, with a wide radius bend into the void of the Timber Floor. If possible the conduit will be situated up to 2m in from the wall, the conduit end must always be accessible, this is to allow for the sensor probe to be inserted or removed for servicing etc. For further information regarding the sensor probes see Thermostat Specifications.
  • (The Site Electrical Contractor must insert the sensor probe, (which is located in the Thermostat box) into this conduit. The sensor must then be connected to the Thermostat.)
  • All heating systems must be connected to a 30 mA Residual Current Device.
  • Thermostat locations should be supplied in writing, no less than 10 days before installation. If these are not received in time, we will position the cold tails at our discretion. If re-location of any cold tails is required, this would be done on a 'do and charge' basis only. A written work order confirming payment details is required prior to commencement of any work.
Floorheat Australia - Electric Underfloor Heating